For the rubber playground tiles that less than 40mm thickness, we should use universal glue in installing.
According to the following methods:
★ Clear the concrete floor surface;
★ Drawing the construction line on the edge of the field. Then, put universal glue on the four corners of the playground rubber mats. After about 2~3 minutes, stick the rubber tiles to the ground, and knock on the four corners with light hammer;
★ Cutting the rubber tiles as per the field’s shape;
★ Drawing the construction line on the edge of the field. Then, put universal glue on the four corners of the playground rubber mats. After about 2~3 minutes, stick the rubber tiles to the ground, and knock on the four corners with light hammer;
★ Cutting the rubber tiles as per the field’s shape;
Attention: The ground must be dry and flat.
The rubber floor tiles with more than 40mm thickness can be laid on the ground directly, installing without glue, because the rubber tiles that more than 40mm thickness is very heavy.
没有评论:
发表评论